Thursday, 8 October 2009

End to end test #1

A full end to end test has now been completed - including testing Andy's software which will keep us fully up-to-date on the balloon's exact position. This is the first time that the entire GPS/radio component of the avionics has been given a full shakedown. We have tested individual components - even to the point of seeing the GPS data in Hyperterminal, but this was the very first time that we had seen a live updated position in Google Earth (and Google Maps on Windows Mobile). I'm very happy to report that this first test was successful.

I do have my doubts as to whether we will be ready for launch this weekend. The camera still needs to be programmed to our specification and has to be fully tested. Phil is still concerned about our descent rate with our current 'chute and this also will need testing in conjunction with our 'release candidate' capsule. With so much achieved so far, well beyond our original concept (check the early posts!), we won't be rushing to launch before everything is confirmed to be flight ready.

Radio TX/RX - Flight Ready
Ground Antenna - Flight Ready
GPS Hardware - Flight Ready
Tracking Software - Flight Ready
Windows Mobile - Flight Ready
Camera - To be programmed
Gas (He) - To be purchased 24 hours before launch
Parachute - Testing required
Capsule - Testing required